Installation of equipment at EU-Funded St. Lucia Hospital

06.10.2016
Teaser

Substantial progress made in terms of installation of equipment at the EU funded state of the art Owen King Hospital in St. Lucia.

Main Image
Text

Substantial progress has been made in terms of installation of equipment – valued at 9m million euros – at the EU funded state of the art Owen King Hospital in St. Lucia. To date all items have been delivered and the largest part installed. Only small parts of the equipment of two out of seven lots remain to be installed and this should be undertaken within the coming weeks. One of the critical steps in the next few weeks also is the related training of personnel. Finalisation of installation and training is expected to be concluded by the end of this year.